The project comprised of a major earth works exercise to release 50% of the site from the flood plain in which it was located, the creation of a new secondary river channel to provide flood compensation storage and the stabilisation of 90,000m3 of sewage sludge.
All the highways and infrastructure were designed to adoptable standards, including a new foul water pumping station.
A balancing pond with reed beds allied to the new river channel provided a 50m wide environmental corridor.
To date over one million sq ft of the warehouse’s have been constructed on this site.