The structure comprises a steelwork frame supporting exposed precast concrete planks, which assist in the thermal performance of the building. The footprint is split level over a former basement of 6 metres in depth. The existing retaining structure was utilised within the final design and the new building was carefully co-ordinated to ensure the wall had minimum impact on the spacial planning of the structure. A detailed analysis of the ground engineering solution was carried out in conjunction with the geotechnical consultants, to value engineer the ground solution given the difficult site constraints.
For further information please contact Project Director, Dave Copeland